Earlier this week, Lok Sabha passed the Bill that provides for the allocation of coal mines that were cancelled by the Supreme Court last year.  In light of this development, this post looks at the issues surrounding coal block allocations and what the 2015 Bill seeks to achieve.

In September 2014, the Supreme Court cancelled the allocations of 204 coal blocks.  Following the Supreme Court judgement, in October 2014, the government promulgated the Coal Mines (Special Provisions) Ordinance, 2014 for the allocation of the cancelled coal mines.  The Ordinance, which was replaced by the Coal Mines (Special Provisions) Bill, 2014, could not be passed by Parliament in the last winter session, and lapsed. The government then promulgated the Coal Mines (Special Provisions) Second Ordinance, 2014 on December 26, 2014.  The Coal Mines (Special Provisions) Bill, 2015 replaces the second Ordinance and was passed by Lok Sabha on March 4, 2015. Why is coal considered relevant? Coal mining in India has primarily been driven by the need for energy domestically.  About 55% of the current commercial energy use is met by coal.  The power sector is the major consumer of coal, using about 80% of domestically produced coal. As of April 1, 2014, India is estimated to have a cumulative total of 301.56 billion tonnes of coal reserves up to a depth of 1200 meters.  Coal deposits are mainly located in Jharkhand, Odisha, Chhattisgarh, West Bengal, Madhya Pradesh, Andhra Pradesh and Maharashtra. How is coal regulated? The Ministry of Coal has the overall responsibility of managing coal reserves in the country.  Coal India Limited, established in 1975, is a public sector undertaking, which looks at the production and marketing of coal in India.  Currently, the sector is regulated by the ministry’s Coal Controller’s Organization. The Coal Mines (Nationalisation) Act, 1973 (CMN Act) is the primary legislation determining the eligibility for coal mining in India.  The CMN Act allows private Indian companies to mine coal only for captive use.  Captive mining is the coal mined for a specific end-use by the mine owner, but not for open sale in the market.  End-uses currently allowed under the CMN Act include iron and steel production, generation of power, cement production and coal washing.  The central government may notify additional end-uses. How were coal blocks allocated so far? Till 1993, there were no specific criteria for the allocation of captive coal blocks.  Captive mining for coal was allowed in 1993 by amendments to the CMN Act.  In 1993, a Screening Committee was set up by the Ministry of Coal to provide recommendations on allocations for captive coal mines.  All allocations to private companies were made through the Screening Committee.  For government companies, allocations for captive mining were made directly by the ministry.  Certain coal blocks were allocated by the Ministry of Power for Ultra Mega Power Projects (UMPP) through tariff based competitive bidding (bidding for coal based on the tariff at which power is sold).  Between 1993 and 2011, 218 coal blocks were allocated to both public and private companies under the CMN Act. What did the 2014 Supreme Court judgement do? In August 2012, the Comptroller and Auditor General of India released a report on the coal block allocations. CAG recommended that the allocation process should be made more transparent and objective, and done through competitive bidding. Following this report, in September 2012, a Public Interest Litigation matter was filed in the Supreme Court against the coal block allocations.  The petition sought to cancel the allotment of the coal blocks in public interest on grounds that it was arbitrary, illegal and unconstitutional. In September 2014, the Supreme Court declared all allocations of coal blocks, made through the Screening Committee and through Government Dispensation route since 1993, as illegal.  It cancelled the allocation of 204 out of 218 coal blocks.  The allocations were deemed illegal on the grounds that: (i) the allocation procedure followed by the Screening Committee was arbitrary, and (ii) no objective criterion was used to determine the selection of companies.  Further, the allocation procedure was held to be impermissible under the CMN Act. Among the 218 coal blocks, 40 were under production and six were ready to start production.  Of the 40 blocks under production, 37 were cancelled and of the six ready to produce blocks, five were cancelled.  However, the allocation to Ultra Mega Power Projects, which was done via competitive bidding for lowest tariffs, was not declared illegal. What does the 2015 Bill seek to do? Following the cancellation of the coal blocks, concerns were raised about further shortage in the supply of coal, resulting in more power supply disruptions.  The 2015 Bill primarily seeks to allocate the coal mines that were declared illegal by the Supreme Court.  It provides details for the auction process, compensation for the prior allottees, the process for transfer of mines and details of authorities that would conduct the auction.  In December 2014, the ministry notified the Coal Mines (Special Provisions) Rules, 2014.  The Rules provide further guidelines in relation to the eligibility and compensation for prior allottees. How is the allocation of coal blocks to be carried out through the 2015 Bill? The Bill creates three categories of mines, Schedule I, II and III.  Schedule I consists of all the 204 mines that were cancelled by the Supreme Court.  Of these mines, Schedule II consists of all the 42 mines that are under production and Schedule III consists of 32 mines that have a specified end-use such as power, iron and steel, cement and coal washing. Schedule I mines can be allocated by way of either public auction or allocation.  For the public auction route any government, private or joint venture company can bid for the coal blocks.  They can use the coal mined from these blocks for their own consumption, sale or for any other purpose as specified in their mining lease.  The government may also choose to allot Schedule I mines to any government company or any company that was awarded a power plant project through competitive bidding.  In such a case, a government company can use the coal mined for own consumption or sale.  However, the Bill does not provide clarity on the purpose for which private companies can use the coal. Schedule II and III mines are to be allocated by way of public auction, and the auctions have to be completed by March 31, 2015.  Any government company, private company or a joint venture with a specified end-use is eligible to bid for these mines. In addition, the Bill also provides details on authorities that would conduct the auction and allotment and the compensation for prior allottees.  Prior allottees are not eligible to participate in the auction process if: (i) they have not paid the additional levy imposed by the Supreme Court; or (ii) if they are convicted of an offence related to coal block allocation and sentenced to imprisonment of more than three years. What are some of the issues to consider in the 2015 Bill? One of the major policy shifts the 2015 Bill seeks to achieve is to enable private companies to mine coal in the future, in order to improve the supply of coal in the market.  Currently, the coal sector is regulated by the Coal Controller’s Organization, which is under the Ministry of Coal.  The Bill does not establish an independent regulator to ensure a level playing field for both private and government companies bidding for auction of mines to conduct coal mining operations.   In the past, when other sectors have opened up to the private sector, an independent regulatory body has been established beforehand.  For example, the Telecom Regulatory Authority of India, an independent regulatory body, was established when the telecom sector was opened up for private service providers.  The Bill also does not specify any guidelines on the monitoring of mining activities by the new allottees. While the Bill provides broad details of the process of auction and allotment, the actual results with regards to money coming in to the states, will depend more on specific details, such as the tender documents and floor price.  It is also to be seen whether the new allotment process ensures equitable distribution of coal blocks among the companies and creates a fair, level-playing field for them.  In the past, the functioning of coal mines has been delayed due to delays in land acquisition and environmental clearances.  This Bill does not address these issues.  The auctioning of coal blocks resulting in improving the supply of coal, and in turn addressing the problem of power shortage in the country, will also depend on the efficient functioning of the mines,  in addition to factors such as transparent allocations.

Finances of the Railways were presented along with the Union Budget on February 1, 2018 (the Railways Budget was merged with the Union Budget last year).  In the current Budget Session, Lok Sabha is scheduled to discuss the allocation to the Ministry of Railways.  In light of this, we discuss Railways’ finances, and issues that the transporter has been facing with regard to financing.

What are the different sources of revenue for Railways?

Indian Railways has three primary sources of revenue: (i) its own internal resources (revenue from freight and passenger traffic, leasing of railway land, etc.), (ii) budgetary support from the central government, and (iii) extra budgetary resources (such as market borrowings, institutional financing).

Figure 1Railways’ internal revenue for 2018-19 is estimated at Rs 2,01,090 crore which is 7% higher than the revised estimates of 2017-18.  Majority of this revenue comes from traffic (both freight and passenger), and is estimated at Rs 2,00,840 crore.  In the last few years, Railways has been struggling to run its transportation business, and generate its own revenue.  The growth rate of Railways’ earnings from its core business of running freight and passenger trains has been declining.  This is due to a decline in the growth of both freight and passenger traffic (see Figure 1).  Railways is also slowly losing traffic share to other modes of transport such as roads and airlines.  The share of Railways in total freight traffic has declined from 89% in 1950-51 to 30% in 2011-12.

 

The Committee on Restructuring Railways (2015) had observed that raising revenue for Railways is a challenge because: (i) investment is made in projects that do not have traffic and hence do not generate revenue, (ii) the efficiency improvements do not result in increasing revenue, and (iii) delays in projects results in cost escalation, which makes it difficult to recover costs.  Railways also provides passenger fares that are heavily subsidised, which results in the passenger business facing losses of around Rs 33,000 crore in a year (in 2014-15).  Passenger fares are also cross-subsidised by charging higher rates for freight.  The consequence is that freight rates have been increasing which has resulted in freight traffic moving towards roads.

Figure 2Figure 2 shows the trends in capital outlay over the last decade.  A decline in internal revenue generation has meant that Railways funds its capital expenditure through budgetary support from the central government and external borrowings.  While the support from central government has mostly remained consistent, Railways’ borrowings have been increasing.  Various committees have noted that an increased reliance on borrowings will further exacerbate the financial situation of Railways.

The total proposed capital outlay (or capital expenditure) for 2018-19 is Rs 1,48,528 crore which is a 24% increase from the 2017-18 revised estimates (Rs 1,20,000 crore).  Majority of this capital expenditure will be financed through borrowings (55%), followed by the budgetary support from the central government (37%).  Railways will fund only 8% of its capital expenditure from its own internal resources.

How can Railways raise more money?

The Committee on Restructuring Railways had suggested that Railways can raise more revenue through private participation in the following ways: (i) service and management contracts, (ii) leasing to and from the private sector, (iii) joint ventures, and (iv) private ownership.  However, private participation in Railways has been muted as compared to other sectors such as roads, and airports.

Figure 3One of the key reasons for the failure of private participation in Railways is that policy making, the regulatory function, and operations are all vested within the same organisation, that is, the Ministry of Railways.  Railways’ monopoly also discourages private sector entry into the market.  The Committee on Restructuring Railways had recommended that the three roles must be separated from each other.  It had also recommended setting up an independent regulator for the sector.  The regulator will monitor whether tariffs are market determined and competitive.

Where does Railways spend its money?

The total expenditure for 2018-19 is projected at Rs 1,88,100 crore, which is 4% higher than 2017-18.  Staff wages and pension together comprise more than half of the Railways’ expenditure.  For 2018-19, the expenditure on staff is estimated at Rs 76,452 crore.  Allocation to the Pension Fund is estimated at Rs 47,600 crore.  These constitute about 66% of the Railways’ expenditure in 2018-19.

Railways’ primary expenditure, which is towards the payment of salaries and pension, has been gradually increasing (with a jump of around 15% each year in 2016-17 and 2017-18 due to implementation of the Seventh Pay Commission recommendations).  Further, the pension bill is expected to increase further in the years to come, as about 40% of the Railways staff was above the age of 50 years in 2016-17.

The Committee on Restructuring Railways (2015) had observed that the expenditure on staff is extremely high and unmanageable.  This expense is not under the control of Railways and keeps increasing with each Pay Commission revision.  It has also been observed that employee costs (including pensions) is one of the key components that reduces Railways’ ability to generate surplus, and allocate resources towards operations.

What is the allocation towards depreciation of assets?

Railways maintains a Depreciation Reserve Fund (DRF) to finance the costs of new assets replacing the old ones.  In 2018-19, appropriation to the DRF is estimated at Rs 500 crore, 90% lower than 2017-18 (Rs 5,000 crore).  In the last few years, appropriation to the DRF has decreased significantly from Rs 7,775 crore in 2014-15 to Rs 5,000 crore last year.  Provisioning Rs 500 crore towards depreciation might be an extremely small amount considering the scale of infrastructure managed by the Indian Railways, and the requirement to replace old assets to ensure safety.

The Standing Committee on Railways (2015) had observed that appropriation to the DRF is the residual amount after appropriation to the Pension Fund, instead of the actual requirement for maintenance of assets.  Under-provisioning for the DRF has also been observed as one of the reasons behind the decline in track renewals, and procurement of wagons and coaches.

Is there any provision towards safety?

Last year, the Rashtriya Rail Sanraksha Kosh was created to provide for passenger safety.  It was to have a corpus of one lakh crore rupees over a period of five years (Rs 20,000 crore per year).  The central government was to provide a seed amount of Rs 1,000 crore, and the remaining amount would be raised by the Railways from their own revenues or other sources.

As per the revised estimates of 2017-18, no money was allocated towards this fund.  In 2018-19, Rs 5,000 crore has been allocated for it.  With the Railways struggling to meet its expenditure and declining internal revenues, it is unclear how Railways will fund the remaining amount of Rs 95,000 crore for the Rail Sanraksha Kosh.

What happened to the dividend that was waived off last year?

Railways used to pay a return on the budgetary support it received from the government every year, known as dividend.  The rate of this dividend was about 5% in 2015-16.  From 2016-17, the requirement of paying dividend was waived off.  The last dividend amount paid was Rs 8,722 crore in 2015-16.

The Standing Committee on Railways (2017) had noted that part of the benefit from dividend is being utilised to meet the shortfall in the traffic earnings of Railways.  This defeats the purpose of removing the dividend liabilities since they are not being utilised in creating assets or increasing the net revenue of Railways.