The Civil Damage for Nuclear Liability Bill, 2010 has been criticised on many grounds (Also click here), including (a) capping liability for the operator, (b) fixing a low cap on the amount of liability of the operator, and (c) making the operator solely liable. We summarise the main principles of civil nuclear liability mentioned in IAEA's Handbook on Nuclear Law: Strict Liability of the Operator: The operator is held liable regardless of fault. Those claiming compensation do not need to prove negligence or any other type of fault on the part of the operator. The operator is liable merely by virtue of the fact that damage has been caused. Legal channeling of liability on the operator: "The operator of a nuclear installation is exclusively liable for nuclear damage. No other person may be held liable, and the operator cannot be held liable under other legal provisions (e.g. tort law)...This concept is a feature of nuclear liability law unmatched in other fields of law." The reason for this has been quoted in the Handbook as:
"...Firstly, it is desirable to avoid difficult and lengthy questions of complicated legal cross-actions to establish in individual cases who is legally liable. Secondly, such channelling obviates the necessity for all those who might be associated with construction or operation of a nuclear installation other than the operator himself to take out insurance also, and thus allows a concentration of the insurance capacity available.”
Limiting the amount of liability: "Limitation of liability in amount is clearly an advantage for the operator. Legislators feel that unlimited liability, or very high liability amounts, would discourage people from engaging in nuclear related activities. Operators should not be exposed to financial burdens that could entail immediate bankruptcy....Whatever figure is established by the legislator will seem to be arbitrary, but, in the event of a nuclear catastrophe, the State will inevitably step in and pay additional compensation. Civil law is not designed to cope with catastrophes; these require special measures." Limitation of liability in time: "In all legal systems there is a time limit for the submission of claims. In many States the normal time limit in general tort law is 30 years. Claims for compensation for nuclear damage must be submitted within 30 years in the event of personal injury and within 10 years in the event of other damage. The 30 year period in the event of personal injury is due to the fact that radiation damage may be latent for a long time; other damage should be evident within the 10 year period." Insurance coverage: "The nuclear liability conventions require that the operator maintain insurance or provide other financial security covering its liability for nuclear damage in such amount, of such type and in such terms as the Installation State specifies....This ensures that the liability amount of the operator is always covered by an equal amount of money. The congruence principle is to the advantage both of the victims of a nuclear incident and of the operator. The victims have the assurance that their claims are financially covered, and the operator has funds available for compensation and does not need to convert assets into cash.
On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM). According to the report most of the projects initiated under JNNURM have not been completed. For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed. Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed. Some of the other key recommendations of the report are:
The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 . With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms. With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006. The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census). JNNURM has two main components namely : (i) Urban Infrastructure and Governance and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance. This implies that the funds are provided as grants to the states directly from the centre. In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM. The table below shows the status of the sanctioned JNNURM projects in the different states. State wise status of the projects under JNNURM (as on August 6, 2012)
Name of State | Total Allocation (Rs Lakh) | Number of sanctioned projects | Completed Projects |
Andhra Pradesh | 2,11,845 | 52 | 18 |
Arunachal Pradesh | 10,740 | 3 | NA |
Assam | 27,320 | 2 | NA |
Bihar | 59,241 | 8 | NA |
Chandigarh | 27,087 | 3 | NA |
Chattisgarh | 24,803 | 1 | NA |
Delhi | 2,82,318 | 23 | 4 |
Goa | 12,094 | 2 | NA |
Gujarat | 2,57,881 | 72 | 40 |
Haryana | 32,332 | 4 | NA |
Himachal Pradesh | 13,066 | 5 | NA |
Jammu & Kashmir | 48,836 | 5 | NA |
Jharkhand | 94,120 | 5 | NA |
Karnataka | 1,52,459 | 47 | 22 |
Kerala | 67,476 | 11 | NA |
Madhya Pradesh | 1,32,850 | 23 | 7 |
Maharashtra | 5,50,555 | 80 | 21 |
Manipur | 15,287 | 3 | NA |
Meghalaya | 15,668 | 2 | NA |
Mizoram | 14,822 | 4 | NA |
Nagaland | 11,628 | 3 | NA |
Orissa | 32,235 | 5 | NA |
Punjab | 70,775 | 6 | 1 |
Puducherry | 20,680 | 2 | NA |
Rajasthan | 74,869 | 13 | 2 |
Sikkim | 10,613 | 2 | NA |
Tamil Nadu | 2,25,066 | 48 | 12 |
Tripura | 14,018 | 2 | NA |
Uttar Pradesh | 2,76,941 | 33 | 4 |
Uttarakhand | 40,534 | 14 | NA |
West Bengal | 3,21,840 | 69 | 15 |
Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.