Early this week, the Comptroller and Auditor General (CAG) of India tabled a report on the finances of Uttar Pradesh for the financial year 2020-21. A few days prior to that, on May 26, the budget for Uttar Pradesh for 2022-23 was presented, along with which the final audited expenditure and receipt figures for the year 2020-21 were released. The year 2020-21 presented a two-fold challenge for states – loss in revenue due to impact of COVID-19 pandemic and lockdown, and the need for increased expenditure to support affected persons and economic recovery. CAG noted that Uttar Pradesh’s GSDP grew by 1.05% in 2020-21 as compared to a growth of 6.5% in 2019-20. The state reported a revenue deficit of Rs 2,367 crore in 2020-21 after reporting revenue surplus for 14 successive years since 2006-07. Revenue deficit is the excess of revenue expenditure over revenue receipts. This blog looks at the key trends in the finances of Uttar Pradesh in 2020-21 and certain observations by CAG on fiscal management by the state.
Spending and Deficits in 2020-21
Underspending: In 2020-21, total spending by the state was 26% less than the budget estimate presented in February 2020. In sectors such as water supply and sanitation, the actual expenditure was 60% less than the amount budgeted, while in agriculture and allied activities only 53% of the budgeted amount was spent. CAG observed that in 251 schemes across 57 departments, the state government did not incur any expenditure in 2020-21. These schemes had a budget provision of at least one crore rupees, and had cumulative allocation of Rs 50,617 crore. These included schemes such as Pipe Drinking Water Scheme in Bundelkhand/Vindhya and apportionment of pension liabilities. Moreover, the overall savings due to non-utilisation of funds in 2020-21 was 27.28% of total budget provisions. CAG observed that the budgetary provisions increased between 2016 and 2021. However, the utilisation of budget provisions reduced between 2018-19 and 2020-21.
Pattern of spending: CAG observed that in case of 12 departments, more than 50% of the expenditure was incurred in March 2021, the last month of the financial year. In the civil aviation department, 89% of the total expenditure was incurred in March while this figure was 62% for the social welfare department (welfare of handicapped and backward classes). CAG noted that maintaining a steady pace of expenditure is a sound practice under public financial management. However, the Uttar Pradesh Budget Manual has no specific instructions for preventing such bunching of expenditure. The CAG recommended that the state government can consider issuing guidelines to control the rush of expenditure towards the closing months of the financial year.
Management of deficit and debt: As a measure to mitigate the impact of COVID-19, an Ordinance was promulgated in June 2020 to raise the fiscal deficit limit from 3% of GSDP to 5% of GSDP for the year 2020-21. Fiscal deficit represents the gap between expenditure and receipts in a year, and this gap is filled with borrowings. The Uttar Pradesh Fiscal Responsibility and Budget Management Act, 2004 (FRBM Act) passed by Uttar Pradesh Assembly specifies the upper limit for debt and deficits. The Ordinance thus permitted the state government to borrow more to sustain its budget expenditure. The fiscal deficit of the state in 2020-21 was 3.20% of GSDP, well below the revised limit. At the same time, the state’s outstanding debt to GSDP in 2020-21 was 32.77% of GSDP, above the target of 32% of GSDP set under the FRBM Act. Outstanding debt represents accumulation of debt over the years.
Table 1: Spending by Uttar Pradesh in 2020-21 as compared to Budget Estimates (in Rs crore)
Particular |
2020-21 BE |
2020-21 Actuals |
% change from BE to Actuals |
Net Receipts (1+2) |
4,24,767 |
2,97,311 |
-30% |
1. Revenue Receipts (a+b+c+d) |
4,22,567 |
2,96,176 |
-30% |
a. Own Tax Revenue |
1,58,413 |
1,19,897 |
-24% |
b. Own Non-Tax Revenue |
31,179 |
11,846 |
-62% |
c. Share in central taxes |
1,52,863 |
1,06,687 |
-30% |
d. Grants-in-aid from the Centre |
80,112 |
57,746 |
-28% |
Of which GST compensation grants |
7,608 |
9,381 |
23% |
2. Non-Debt Capital Receipts |
2,200 |
1,135 |
-48% |
3. Borrowings |
75,791 |
86,859 |
15% |
Of which GST compensation loan |
- |
6,007 |
- |
Net Expenditure (4+5+6) |
4,77,963 |
3,51,933 |
-26% |
4. Revenue Expenditure |
3,95,117 |
2,98,543 |
-24% |
5. Capital Outlay |
81,209 |
52,237 |
-36% |
6. Loans and Advances |
1,637 |
1,153 |
-30% |
7. Debt Repayment |
34,897 |
26,777 |
-23% |
Revenue Balance |
27,451 |
-2,367 |
-109% |
Revenue Balance (as % of GSDP) |
1.53% |
-0.14% |
|
Fiscal Deficit |
53,195 |
54,622 |
3% |
Fiscal Deficit (as % of GSDP) |
2.97% |
3.20% |
Note: A negative revenue balance indicates a deficit. The actual fiscal deficit reported by Uttar Pradesh for 2020-21 in 2022-23 budget was 2.8% of GSDP. This difference was due to higher GSDP figure reported by the state.
Sources: Uttar Pradesh Budget Documents of various years; CAG; PRS.
Finances of State Public Sector Undertakings
Public sector undertakings (PSUs) are set up by the government to discharge commercial activities in various sectors. As on March 31, 2021, there were 115 PSUs in Uttar Pradesh. CAG analysed the performance of 38 PSUs. Out of these 38 PSUs, 22 companies earned a profit of Rs 700 crore, while 16 companies posted a loss of Rs 7,411 crore in 2020-21. Note that both the number of PSUs incurring losses and the quantum of losses has decreased since 2018-19. In 2018-19, 20 PSUs had reported losses worth Rs 15,219 crore.
Figure 1: Cumulative losses incurred by Uttar Pradesh PSUs (Rs crore)
Sources: CAG; PRS.
Losses of power sector PSUs: Three power sector PSUs—Uttar Pradesh Power Corporation Limited, Purvanchal Vidyut Vitran Nigam Limited, and Paschimanchal Vidyut Vitran Nigam Limited—were the top loss incurring PSUs. These three PSUs accounted for 73% of the total losses of Rs 7,411 crore mentioned above. Note that as of June 2022, for each unit of power supplied, the revenue realised by UP power distribution companies (discoms) is 27 paise less than cost of supply. This is better than the gap of 34 paise per unit at the national level. However, the aggregate technical and commercial losses (AT&C) of the Uttar Pradesh discoms was 27.85%, considerably higher than the national average of 17.19%. AT&C losses refer to the proportion of power supplied by a discom for which it does not receive any payment.
Off-budget borrowings: CAG also observed that the Uttar Pradesh government resorted to off-budget borrowing through state owned PSUs/authorities. Off budget borrowings are not accounted in the debt of the state government and are on books of the respective PSUs/authorities, although, debt is serviced by the state government. As a result, the outstanding debt reported in the budget does not represent the actual debt position of the state. CAG identified off-budget borrowing worth Rs 1,637 crore. The CAG recommended that the state government should avoid extra-budget borrowings. It should also credit all the loans taken by PSUs/authorities on behalf of and serviced by the state government to state government accounts.
Management of Reserve Funds
The Reserve Bank of India manages two reserve funds on the behalf of state governments. These funds are created to meet the liabilities of state governments. These funds are: (i) Consolidated Sinking Fund (CSF), and (ii) Guarantee Redemption Fund (GRF). They are funded by the contributions made by the state governments. CSF is an amortisation fund which is utilised to meet the repayment obligations of the government. Amortisation refers to payment of debt through regular instalments. The interest accumulated in the fund is used for repayment of outstanding liabilities (which is the accumulation of total borrowings at the end of a financial year, including any liabilities on the public account).
In line with the recommendation of the 12th Finance Commission, Uttar Pradesh created its CSF in March 2020. The state government may transfer at least 0.5% of its outstanding liabilities at the end of the previous year to the CSF. CAG observed that in 2020-21, Uttar Pradesh appropriated only Rs 1,000 crore to the CSF against the requirement of Rs 2,454 crore. CAG recommended that the state government should ensure at least 0.5% of the outstanding liabilities are contributed towards the CSF every year.
GRF is constituted by states to meet obligations related to guarantees. The state government may extend guarantee on loans taken by its PSUs. Guarantees are contingent liabilities of the state government, as in case of default by the company, repayment burden will fall on the state government. GRF can be used to settle guarantees extended by the government with respect to borrowings of state PSUs and other bodies. The 12th Finance Commission had recommended that states should constitute GRF. It was to be funded through guarantees fees to meet any sudden discharge of obligated guarantees extended by the states. CAG noted that Uttar Pradesh government has not constituted GRF. Moreover, the state has also not fixed any limits for extending guarantees.
For an analysis of Uttar Pradesh’s 2022-23 budget, please see here.
Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii] The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity. The scheme is expected to cover three crore households. Note that currently about four crore households are un-electrified. A rural electrification scheme has also been under implementation since 2005. In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.
Regulatory and policy framework
Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas. The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas. Consequently, the Rural Electrification Policy was notified in August 2006.[iii]
The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification. In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv] Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.
The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore. The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.
Status of rural electrification
As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages). However, with regard to households, around 23% (4.1 crore households) are yet to be electrified. Table 1 at the end of this post shows the status of rural electrification across all states.
Issues with rural electrification
Definition of an electrified village
An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]
Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified. This is apart from the basic infrastructure and electrification of certain public centers in the village. The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v] It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable. The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.
Supply of electricity
The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v] These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages. Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses. Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%. While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.
It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]
Electricity to below poverty line (BPL) households
Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000. It has been observed that this cost per household may be inadequate.[v] Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme. It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]
The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)
The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas. Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data. The identified poor households will get free electricity connections. Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500. This amount will be collected by the electricity distribution companies in 10 instalments.
The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore. The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore. For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.
The state discoms will execute the electrification works through contractors or other suitable agencies. Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries. In order to accelerate the process, applications for electricity connections will be completed on the spot.
So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide. Saubhagya extends the ambit of electrification projects to urban areas as well. While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification. While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity. Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.
Table 1: Status of rural electrification across states (as of August 2017)
[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.
[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.
[iii]. Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.
[iv]. “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.
[v]. “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.