Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.
Elections to the 13th Legislative Assembly of Gujarat are scheduled to be held in two phases on the 13th and 17th of December. The BJP has been the dominant majority party in the Assembly since 1995. The 2002 elections saw the largest victory for the party, winning 127 seats. The Congress last held power in Gujarat in 1985. In the Assembly elections held for the the seventh Assembly, the Congress had a clear majority of 149 seats. In 1990, the Janata Dal emerged as the largest party with 70 seats. The BJP registered major gains in 1990, improving their tally of 11 seats in 1985 to 67 seats. The Congress came third with 33 seats. The electoral trends over the last 22 years may be viewed here. In the current Assembly, 117 of the 182 seats are held by the BJP. It is useful to look at the work done by the 12th Gujarat Assembly during its term from 2008 to 2012. Here we look at key metrics like the number of days the assembly was in session, members’ attendance, and legislative business. Performance of the Assembly During its five year term, the assembly sat for a total of 157 days – an average of 31 days each year. In comparison, the Lok Sabha sat for an average of 66 days each year during the period 2008 to 2011. In the same period the Kerala Assembly sat for an average of 50 days – highest among states - followed by Maharashtra (44). However, the Gujarat Assembly sat for more number of days than the Haryana Assembly which sat for an average of 13 days and Rajasthan (24). The average attendance among Gujarat MLAs stood at 83% for the whole term, with two members registering 100% attendance. 87 Bills were passed by the Assembly since the beginning of its term in 2008 till September 2011. Of these, 80 Bills i.e. over 90% of all Bills were passed on the same day as they were introduced. None of the Bills were referred to any Committee. In the Budget Session of 2011, 31 Bills were passed of which 21 were introduced and passed within three sitting days Amendments sought by the President and the Governor One of the significant laws passed by the 12th Assembly was the Gujarat Control of Terrorism and Organised Crime Bill, 2003 which was introduced and passed in July 2009. However the Bill did not receive the Presidents Assent and was sent back to the Gujarat Assembly for amendments. In December 2009, the assembly passed the Gujarat Local Authorities Laws (Amendment) Bill 2009 which sought to make voting compulsory in elections to local self-government bodies like municipal corporations and Panchayats. The Gujarat governor returned the Bill for reconsideration in 2010. It was re-introduced in the house in September 2010 without changes. Another Bill that was returned by the Governor was the Gujarat Regularisation of Unauthorised Development Bill which sought to regularise unauthorised construction on payment of an Impact Fee. The Bill was passed by the Assembly in March 2011. The Governor returned the Bill with a suggestion to include a provision to bar the regularisation of unauthorised construction beyond a specified date. The Bill was re-introduced and passed with amendments by the Assembly in September 2011.
In the last decade, the government has implemented several schemes to address issues related to urbanisation and aid the process of urban development. One of the schemes is the Smart Cities Mission, which intends to take advantage of the developments in information technology in developing the urban development strategy, across 100 cities. Last week the government announced the list of 9 new Smart Cities, taking the total to 99. In light of this, we look at the Smart Cities Mission and a few issues with it.
What is a Smart City?
The primary objective of the Mission is to develop cities that provide core infrastructure and give a decent quality of life to its citizens, a clean and sustainable environment, and apply ‘smart’ solutions.
However, the Mission document does not provide one definition of a Smart City. Instead it allows cities to come up with their own solutions of what they identify as a Smart City. The guidelines suggest that the core infrastructure elements in a Smart City will include: (i) adequate water supply, (ii) assured electricity supply, (iii) sanitation, including solid waste management, (iv) efficient urban mobility and public transport, (v) affordable housing, (vi) robust IT connectivity, and (vii) good governance. ‘Smart’ solutions may include (i) energy efficient buildings, (ii) electronic service delivery, (iii) intelligent traffic management, (iv) smart metering, (v) citizen engagement, etc.
How were the Smart Cities selected?
The Mission was introduced in the form of a competition, called the Smart City challenge. The first stage was in July 2015 when states nominated their cities for the competition. In August 2015, the Ministry of Urban Development selected 100 of those cities to participate in the competition. These cities were required to develop their smart city plans (SCPs) and compete against each other. The SCPs were evaluated on the basis of the solutions, the processes followed, the feasibility and cost effectiveness of the plans, and citizen engagement. Over the last 2 years, the Ministry has announced winner cities in batches. So far, 99 cities have been selected under the Mission.
What information do these SCPs contain?
The cities had to prepare their SCPs with two primary strategic components: (i) area-based development, and (ii) pan-city development. The area-based development would cover a particular area of the city, and could have either a redevelopment model, or be a completely new development. Pan-city development would envisage application of certain smart solutions across the city to the existing infrastructure.
Each city had to formulate its own concept, vision, mission and plan for a Smart City that was appropriate to its local context and resources. The Ministry of Urban Development provided technical assistance, through consultancy firms, to cities for helping them prepare these strategic documents.
How will the Mission be implemented?
The Mission will be implemented at the city level by a Special Purpose Vehicle (SPV). The SPV will plan, approve, release funds, implement, manage, monitor, and evaluate the Smart City development projects.
The SPV will be a limited company incorporated under the Companies Act, 2013 at the city-level. It will be chaired by the Collector/ Municipal Commissioner of the Urban Development Authority. The respective state and the Urban Local Body (ULB or municipality) will be the promoters in this company having 50:50 equity shareholding.
How are the Plans getting financed?
The Mission will be operated as a Centrally Sponsored Scheme. The central government will provide financial support of up to Rs 48,000 crore over five years, that is, an average of Rs 500 crore per city. The states and ULBs will have to contribute an equal amount. The central government allocated Rs 4,000 crore towards the Mission in the 2017-18 budget.
Since funding from the government will meet only a part of the funding required, the rest will have to be raised from other sources including: (i) states/ ULBs own resources from collection of user fees, land monetization, etc., (ii) innovative finance mechanisms such as municipal bonds, (iii) leverage borrowings from financial institutions (such as banks), and (iv) the private sector through Public Private Partnerships (PPPs).
The total cost of projects proposed under the various SCPs of the 90 winner cities is Rs 1.9 lakh crore. About 42% of this amount will come from central and state funding, 23% through private investments and PPPs, and 19% through convergence with other schemes (such as HRIDAY, AMRUT, Swachh Bharat-Urban). The remaining will be generated by the cities through the levy of local taxes, and user fees.
What are some of the issues to consider?
Financial capacity of cities: Under the Mission, cities have to generate additional revenue through various sources including market borrowings, PPPs, and land monetization. The High Powered Expert Committee on Indian Urban Infrastructure and Services (HPEC) had observed that ULBs in India are among the weakest in the world, both in terms of capacity to raise resources and financial autonomy. Even though ULBs have been getting higher allocations from the centre and states, and tax devolution to them has increased, their own tax bases are narrow. Further, owing to their poor governance and financial situation, ULBs find it difficult to access external financing.
Such a situation may pose problems when implementing the Mission, where the ULBs have to raise a significant share of the revenue through external sources (PPPs, market borrowings). For example, the Bhubaneswar Smart City Plan has a total project cost of Rs 4,537 crore (over five years), while the city’s annual budget for 2014-15 was Rs 469 crore.
In order to improve the finances of the ULBs, committees have made various recommendations, which include:
The government has recently introduced a few policies and mechanisms to address municipal financing. Examples include value capture financing through public investments in infrastructure projects, and a credit rating system for cities. In June 2017, the Pune Municipal Corporation raised Rs 200 crore by issuing municipal bonds.
Technical capacity of the ULBs: The Smart Cities Mission seeks to empower ULBs to raise their own revenue, and also lays emphasis on the capacity building of ULBs. The HPEC had observed that municipal administration has suffered due to: (i) presence of untrained and unskilled manpower, and (ii) shortage of qualified technical staff and managerial supervisors. It had recommended improving the technical capacity of ULBs by providing technical assistance to state governments, and ULBs in planning, financing, monitoring, and operation of urban programmes. The central government had allocated Rs 10.5 crore towards the capacity building component of the Mission in 2017-18.
The Ministry of Urban Development has been running several programmes to improve capacity of ULBs. This includes MoUs with 18 states to conduct training programmes for their ULB staff.
Coverage of the Mission: The Mission covers 100 cities, of which 99 have been announced as winners so far. The urban population that will be impacted through the Mission is around 96 million (data for 90 cities excluding the recently announced 9 cities).
As per Census 2011, India’s urban population was 377 million. The Mission impacts about 25% of this population. Further, most of the SCPs approved so far focus on area-based development, thus affecting a particular area of the cities. About 80% of the total project cost proposed is towards this model of development. In each city, this area-based development will cover up to 50 acres of area. The remaining 20% of the project cost is towards pan-city development proposals, which provide smart planning solutions for the entire city. It may be argued that even within the selected cities, the Mission will only impact few selected areas, and not necessarily help with development of the entire city.