Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified when applications open.
In India, one of the common threads that run through many of the corruption scandals is the issue of conflict of interest i.e. public officials taking policy decisions based on their personal interest. For example, Shashi Tharoor in the IPL controversy or Ashok Chavan in the Adarsh Housing Society scam. Many countries take measures to minimize conflict of interest of its MPs by regulating membership of parliamentarians in Committees, making it mandatory for them to declare pecuniary interest, and restricting employment both during and after completion of tenure. For example, the US Senate has a detailed Code of Official Conduct that provides guidelines on conflict of interest. India also has some measures in place to minimize conflict of interest. These are codified in the Code of Conduct for Ministers, Code of Conduct for Members of the Rajya Sabha, Rules of Procedure and Conduct of Business in the Lok Sabha and Rajya Sabha and Handbook for Members of Lok Sabha and Rajya Sabha. Every Rajya Sabha MP has to declare his or her interest (along with assets and liabilities). He has to declare five pecuniary interests: remunerative directorship, remunerated activity, majority shareholding, paid consultancy and professional engagement. Lok Sabha MPs can object to another MP joining a parliamentary committee on grounds that he has personal, pecuniary or direct interest. (For more details, see PRS note on Conflict of Interest Issues in Parliament). On December 1, 2010, PRS held its annual Conference on Effective Legislatures. One of the topics discussed was MPs and Conflict of Interest: Issues and Resolution. Panelists included D Raja, Prakash Javdekar and Supriya Sule. Issues such as requirement for transparency, expertise of legislators, election of honest legislators, and ethical media were discussed. The issues that were raised during the discussion are summarised in the PRS Summary of Proceedings from the Conference.
There has been no resolution so far to the issue of assured fuel supply from Coal India Limited (CIL) to power producers. According to reports, while CIL released a model supply agreement in April 2012, so far only around 13 Fuel Supply Agreements (FSAs) have been signed. Originally around 50 power units were expected to sign FSAs with CIL. Power producers have objected to the model FSA released by CIL, particularly its force majeure provisions and the dilution of financial penalties in case of lower than contracted supply. Background The adverse power supply situation has attracted greater attention in the past few months. According to Central Electricity Authority's data, the gap between peak demand and peak supply of power in March 2012 was 11 per cent. The decreasing availability of fuel has emerged as a critical component of the worsening power supply situation. As of March 31, 2012, there were 32 critical thermal power stations that had a coal stock of less than 7 days. The gap between demand and supply of coal in the past three years is highlighted below: Table 1: Coal demand/Supply gap (In millions of tonnes)
2009-10 |
2010-11 |
2011-12 |
|
Demand |
604 |
656 |
696 |
Supply |
514 |
523 |
535 |
Gap |
90 |
133 |
161 |
Source: PIB News Release dated May 7, 2012 Coal accounts for around 56 per cent of total installed power generation capacity in India. Increased capacity in thermal power has also accounted for almost 81 per cent of the additional 62,374 MW added during the 11th Plan period. Given the importance of coal in meeting national energy needs, the inability of CIL to meet its supply targets has become a major issue. While the production target for CIL was 486 MT for 2011-12, its actual coal production was 436 MT. Fuel Supply Agreements In March 2012, the government asked CIL to sign FSAs with power plants that have been or would be commissioned by March 31, 2015. These power plants should also have entered into long term Power Purchase Agreements with distribution companies. After CIL did not sign FSAs by the deadline of March 31, 2012 the government issued a Presidential Directive to CIL on April 4, 2012 directing it to sign the FSAs. The CIL board approved a model FSA in April 2012, which has not found acceptance by power producers. According to newspaper reports, many power producers have expressed their dissatisfaction with the model FSA released by CIL. They have argued that it differs from the 2009 version of FSAs in some major ways. These include:
Most power producers, including NTPC, the country’s biggest power producer, have refused to sign the new FSA. Reports suggest that the Power Minister has asked the Prime Minister’s Office to mandate CIL to sign FSAs within a month based on the 2009 format. CIL has received a request from NTPC to consider signing FSAs based on the same parameters as their existing plants, but with the revised trigger point of 80 per cent (down from 90 per cent earlier). Underlying this situation is CIL’s own stagnating production. Various experts have pointed to the prohibition on private sector participation in coal mining (apart from captive projects) and the backlog in granting environment and forest clearances as having exacerbated the coal supply situation.