Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified. Last date for submitting the applications is December 21, 2024.

In India, one of the common threads that run through many of the corruption scandals is the issue of conflict of interest i.e. public officials taking policy decisions based on their personal interest.  For example, Shashi Tharoor in the IPL controversy or Ashok Chavan in the Adarsh Housing Society scam. Many countries take measures to minimize conflict of interest of its MPs by regulating membership of parliamentarians in Committees, making it mandatory for them to declare pecuniary interest, and restricting employment both during and after completion of tenure.  For example, the US Senate has a detailed Code of Official Conduct that provides guidelines on conflict of interest. India also has some measures in place to minimize conflict of interest.  These are codified in the Code of Conduct for Ministers, Code of Conduct for Members of the Rajya Sabha, Rules of Procedure and Conduct of Business in the Lok Sabha and Rajya Sabha and Handbook for Members of Lok Sabha and Rajya Sabha.  Every Rajya Sabha MP has to declare his or her interest (along with assets and liabilities).  He has to declare five pecuniary interests:  remunerative directorship, remunerated activity, majority shareholding, paid consultancy and professional engagement.  Lok Sabha MPs can object to another MP joining a parliamentary committee on grounds that he has personal, pecuniary or direct interest.  (For more details, see PRS note on Conflict of Interest Issues in Parliament). On December 1, 2010, PRS held its annual Conference on Effective Legislatures.  One of the topics discussed was MPs and Conflict of Interest: Issues and Resolution.  Panelists included D Raja, Prakash Javdekar and Supriya Sule.  Issues such as requirement for transparency, expertise of legislators, election of honest legislators, and ethical media were discussed.  The issues that were raised during the discussion are summarised in the PRS Summary of Proceedings from the Conference.

The Comptroller and Auditor General (CAG) released a Performance Audit of Allocation of Coal Blocks and Augmentation of Coal Production, on August 17, 2012.  Some of the main findings and recommendations of the report are highlighted below:

  • There were no criteria for allocating coal blocks for captive mining till 1993.  The process of bringing in transparency and objectivity began in January 2004.  However, the process has experienced delays and had yet to materialise as of February 2012.
  • In the intervening period, 194 coal blocks with geological reserves of 44,440 million tonnes were allocated to private and government parties until March 31, 2011.  The report finds that the benefit to private allottees has been estimated at Rs 1.86 lakh crore for Opencast mines.  The report states that the government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The rate of increase in production of coal by Coal India Limited (CIL) during the 11th Plan period remained below the target set by the Planning Commission.  Capacity addition projects were delayed due to the lack of coordination of government agencies involved in statutory clearances and land acquisition.  There were mismatches in excavation and transportation capacities of mines, and suboptimal use of Heavy Earth Moving Machinery.
  • The CAG recommends that Ministry of Coal (MOC) should work out modalities to implement the procedure of allocation of coal blocks for captive mining through competitive bidding.
  • The CAG recommends that the MOC should constitute an empowered group along the lines of Foreign Investment Promotion Board as a single window mechanism for granting clearances, with representatives from central nodal ministries and state governments.

A one-page summary of the main findings and recommendations can be accessed here.  The full report can be accessed on the CAG website.